Carpenters Going Green: Point Breakdown Category 3- Energy and Atmosphere
8 Points Attained

1. Optimize Energy Performance Exceed the American Society of Heating, Refrigerating and Air-Conditioning Engineers ASHRAE 90.1 Energy Standard by 10.5%
2. Optimize Energy Performance Exceed ASHRAE 90.1 by 14%
3. Optimize Energy Performance Exceed ASHRAE 90.1 by 17.5%
4. Optimize Energy Performance Exceed ASHRAE 90.1 by 21%
5. Optimize Energy Performance Exceed ASHRAE 90.1 by 24.5%
6. Optimize Energy Performance Exceed ASHRAE 90.1 by 28%
7. Optimize Energy Performance Exceed ASHRAE 90.1 by 31.5%



The Carpenters Center was modeled in order to predict how much the design of the building would save money in energy use per year. Comparing it to a typical building using the ASHRAE 90.1-2004 Energy Standard, the project uses 31.5% less energy then a typical building



8. Enhanced Refrigerant Management - all HVAC units for this project are specified to use R-410a refrigerant, and therefore do not use either Chlorofluorocarbons (CFCs) or Hydrofluorocarbons (HCFC) refrigerants.

For more information, click on the links in the right column under the heading "Carpenters Going Green"

Wednesday, April 21, 2010

As Seen on the LED Display




Carpenters Going Green: Point Breakdown Category 1- Sustainable Sites
8 Points Attained

1. Site Selection - the site was formerly developed and consists entirely of an existing building and paving.

2. Development Density and Community Connectivity - a dense urban site. Within a .5 mile radius of the building’s main entrance there are at least 2 zones that can be designated as residential zones and many basic services within pedestrian access. Basic services include retail, grocery, banks, restaurants, places of worship, schools and a fire station.

3. Public Transportation Access - located .4 miles from Andrews Station and .3 miles from JFK/UMass. MBTA bus stop in front of building.



4. Bicycle Storage and Changing Rooms -providing covered and secured bicycle storage for a minimum of 5% of the peak building users. The bike racks are located in bike storage room on Level 1 of the garage. One showering facility is required for the 167 occupents - located on level 2 of building.

5. Low-Emission & Fuel Efficient Vehicles - providing preferred parking spaces for low-emitting and fuel-efficient vehicles for 5% of the total parking capacity. Spaces will be signed for low-emitting and fuel-efficient vehicles and will be close to main entrance.

6. Stormwater Design – the project will capture and treat 90% of the average annual rainfall and remove 80% of total suspended solids. There are five 8’ diameter drywells surrounded in crushed stone that will act as a retention system with capacity for infiltration.



7. Heat Island Effect – Non-Roof - 50% of the site hardscape (roads, sidewalks, courtyards and parking lots) have a Solar Reflectance Index (SRI) of at least 29. 63.9% of the project’s hardscape meets that minimum by using a light grey concrete (parking garage deck).

8. Heat Island Effect – Roof - A white high albedo roof for the entire surface – Carlisle SynTec’s Sure-weld TPO white membrane roofing. The roof has a Solar Reflectance Index of 110, which exceeds minimum requirement of SRI 78.



For more information, click on the links in the right column under the heading "Carpenters Going Green"

Wednesday, April 7, 2010

As Seen on the LED Display



Carpenters Going Green - Category 5 - Indoor Enviornmental Quality

Prerequisite - Environmental Tobacco Smoke Control – the entire building has been designated as non-smoking. Any exterior smoking must be 25 feet away from entries, outdoor air intakes and operable windows.

1. Outdoor Air Delivery Monitoring – the building is designed with a permanent CO2 monitoring system in all higher occupancy spaces

2. Increased Ventilation - designed to comply by allowing the mechanical system to provide breathing zone outdoor air ventilation rates and at least 30% above the minimum rates

3. Construction IAQ Management Plan – During Construction Suffolk Construction is committed to implementing a construction IAQ management plan in accordance with LEED requirements

4. Low-Emitting Materials – Adhesives and Sealants (VOC limits) Specified adhesives and sealants that comply with the South Coast Air Quality Management District Rule #1168 and Green Seal Standard

5. Low-Emitting Materials – Paints and Coatings (VOC limits) Project uses paints and coatings inside the building envelope that complies with the Green Seal Standard GS-11 for paints and primers Standard GS-03 for anti-corrosive paints and the South Coast Air Quality Management District Rule 1113 for finishes, stains, and sealer



6. Low-Emitting Materials – Carpet Systems (CRI Green label program and VOC limits). The project uses carpets and carpet cushions that meet the testing and product requirements of the Carpet and Rug Institute’s Green Label Plus Program. All of the carpet’s adhesives will meet VOC limits.



7. Low-Emitting Materials – Composite Wood and Agrifiber Products - Will not use composite wood and agrifiber products that contain urea-formaldehyde resins inside the building’s envelope.

8. Lighting – individual controls for 90% of occupants. There are lighting controls for every regularly occupied space. Private and shared offices have two-level occupancy sensors, individual workstations have flexible, integrally-switched task lights, and classroom/conference spaces have multiple levels of switch controls to allow for adjustment of lighting levels in accordance with the activity.



9. Thermal Comfort Design - targets to maintain 75 degrees and 50% relative humidity in the summer and 72 degrees in the winter.