Friday, September 25, 2009

Drywall Work Continues



This week, drywall work was completed on the third floor of the building, with the exception of the elevator door fronts. Elevator work is expected to begin later next week. When the elevator work begins the door fronts will be drywalled. Drywall crews have started work on the second floor.



Electrical and mechanical inspections of the first floor are scheduled for next week.