Cement Finishers and Laborers working for S&F Concrete completed the concrete pour on the third floor of the building earlier this week.
A view of the 3rd floor q-deck before concrete pour.
After the Q-deck was shot in place, WWF (welded wire fabric) was laid out on top. The WWF serves as reinforcement for the concrete keeping it from expanding to the extent where it will then collapse. The concrete was then pumped into the 3rd floor Q-deck.
Over 350 yards of light weight concrete was poured into the 26,000 square foot space. The work was completed in 12 hours.
View a short video of the process: