Friday, April 24, 2009

Water Tanks Installed, Mockups Fabricated

This week, five storm water septor tanks were installed on site. The tanks will collect drainage from the roof and parking deck so the run off doesn't super charge the water system in the street and cause flooding. These tanks, by design, will slowly disperse water bank into the soil.




Form work for stairwell at the North end of the building continued. The hole seen here is from the original structure and will be filled in with concrete. The carpenter seen here is working on the forms.



12x16 Mockup panels were fabricated and are on display for the Boston Redevelopment Authority (BRA) to display samples of the Alucabond Panels that will cover the exterior of the building as well as the windows. The mock ups will give the BRA an idea of the look and color of the completed building. They will be stay on site for the duration of the project.



A view from Dorchester Ave.